P1 |
When the system is down or not usable by most of the users. |
1 Business Hour |
8 business hours |
P1 |
System is up and running but some business critical process is having issues or needs technical assistance. |
4 Business Hours |
2 working days |
P1 |
One or some of the application components are not working and need attention but of medium priorities. |
8 business hours |
As per the urgency and the estimation of work agreed between two parties |
P1 |
One or some of the application components are not working and need attention but of low priorities. Small enhancements also can be categorized in this bucket. |
2 working days |
As per the urgency and the estimation of work agreed between two parties |
CR |
Any enhancement requests which requires more than 20 hours of effort. |
4 working days |
As per the urgency & the estimation of work agreed between two parties. The estimated hours needs to be approved by customer before the work start |